Rip Kai Construction Update – Foundations


Published 29 Aug 2020

The Encompass team has completed the following foundation groundwork:

  • Steel cages fabricated for piles
  • Batter Board completed
  • Piles for foundations underway
  • Pile clean up and site leveling underway
  • Steel cages for grade beam in production
  • Grade beam installation
  • All Grade beams poured
  • Formwork removed from grade beams
  • Grade beam installation is complete
  • Plumbing Rough-ins are completed for Slab
  • Electrical Rough-ins are completed for slab
  • Steelwork for slab
  • Slab has been poured
  • First floor CMU 90% Completed

To see all the Rip Kai construction updates view the project page here.