The Encompass team has completed the following foundation groundwork:
- Steel cages for grade beam are complete
- All Grade beams poured
- Formwork removed from grade beams
- Grade beam installation is complete
- Working on Slab
- Plumbing Rough-ins are in progress for Slab
- Electrical Rough-ins are in progress for slab
To see more construction updates you can view the full project here.